Road Map for Rajiv Gandhi - Chandigarh Technology Park (RGCTP)

Description

Likely date of completion

PHASE - I  

Infrastructure including Roads, Sewerage, Strom Water, Electricity, Electrical fittings including street lights, Horticulture, Tube-wells landscaping and other work.

Completed

     
  Infosys Technologies Ltd.  
 
  • Phase - I   of Site Development
  • Phase - II  of Site Development
  • Phase - III of Site Development (Under Construction)
Completed
Completed
31.12.2009
  DLF  
 
  • IT / ITES Space
  • Multi-Utility Centre
Completed
Completed
  Build to Suit Sites Work in Progress
  Construction and operationalisation of EDC. Work in progress / Dec. 2009
 

Hotel -cum- Convention Centre Site

Work in Progress

     
PHASE - II  
  Infrastructure including Roads, Sewerage, Strom Water, Electricity, Electrical fittings including street lights, Horticulture, Tube-wells landscaping and other work.  

a)

Road work

Completed

b)

Tube-wells

Completed

c)

Water supply

Completed

d)

Sewerage

Completed

e)

Storm water

Completed

f)

Street lights (Internal)

Completed

g)

Shifting of overhead 66 KV line Circuit I & II through under-ground.

Under Process

 
  • Wipro
  • Tech Mahindra
  • Bharti Airtel
Building Plan Finalized
Work in progress / Dec. 2009
Work in progress / Dec. 2009
PHASE - III  

Acquisition of land for the third phase.

Under Process

 

 
   